Project Details

The scope of the project involved design and installation of a 20-inch gas line service.  The existing line remained operational during construction and was capped after project commissioning. 

  • New construction
  • Replacement of existing line with a 20-inch high pressure gas line
  • 25 service taps
  • 3,200 lineal foot of directional drilling under river bed
  • 11 months of construction
  • EPC contractor

Location: Johnstown, Pennsylvania

Owner: EQT Corporation