Project Details
Mascaro installed the upper reservoir emergency shutoff gate for this operating power generating station.
- General contractor
- Renovation of 107 feet high dam intake structure
- Erect two temporary steel cofferdams 23 feet wide and 30 feet tall with bypass piping
- 2,530 cubic yards of mass concrete
- Install two 12 feet by 30 feet wheel gates with lift assemblies
Location: New Jersey
Owner: First Energy Corp.