Marcellus projects for EQT spread throughout Western Pennsylvania and West Virginia.  Mascaro’s scope of work included excavation, reinforced concrete installation, shoring, and backfill.  The Tioga Tapsite resulted in the construction of a meter station that connects EQT’s resources to the Tennessee Gas El Paso Pipeline.

  • New construction
  • Fast track schedules ranging from one week to one month for Marcellus Wells
  • 8 months of construction on Tioga Tapsite
  • Civil subcontractor to Evets and Power Piping

Location: Pennsylvania

Owner: EQT Corporation