Project Details

The completed  booster compressor station consists of three compressors, process piping, and auxiliary equipment.

  • New construction
  • 30,000 cubic yards excavation for pipe trenches
  • 2,500 cubic yards of concrete
  • 3,700 linear feet of pipe trench inside plant
  • Trenching for 5,000 linear feet of grounding and duct bank
  • 8 months of construction
  • General contractor

Location: Powhatan, Ohio

Owner: Energy Transfer Partners