Project Details
The completed booster compressor station consists of three compressors, process piping, and auxiliary equipment.
- New construction
- 30,000 cubic yards excavation for pipe trenches
- 2,500 cubic yards of concrete
- 3,700 linear feet of pipe trench inside plant
- Trenching for 5,000 linear feet of grounding and duct bank
- 8 months of construction
- General contractor
Location: Powhatan, Ohio
Owner: Energy Transfer Partners