Project Details

The scope includes the installation of three 4160V 2.5Mw diesel generators supplying emergency power, three 2,750 ton chillers supplying chilled water, three 50,000 lb/hr steam boiler systems supplying heating, a three-cell cooling tower,  two 7.5 MVA transformers, insulated metal panels, masonry exterior, and drilled caisson foundations.

  • New construction
  • 35,000 linear feet of underground piping
  • 11 months of construction
  • Design-build

Location: Pittsburgh, Pennsylvania

Owner: NRG