Enable JavaScript to ensure website accessibility Press Building Addition | Mascaro

Press Building Addition

Press Building Addition
Client

Confidential Client

Location Pin

Western Pennsylvania

  • Addition to an existing forge press facility
  • 80,000 square feet
  • 3,555 tons of structural steel
  • 12,000 cubic yards of concrete
  • Building demolition
  • General contractor

Project Details

Construction of a new building addition to house a 10,000-ton open-die press, serviced by a 200-ton rail-bound manipulator, a 100-ton mobile manipulator, and three forging furnaces. Work included excavation, sheet pile, micro piles, equipment foundations, structural building renovations, building additions, duct banks, lighting, power, storm, sanitary, water, process piping, and HVAC.